Meadow Village

Actual Costs – $306,285 ($151,070 ARRA Funds)
Completion Date – November 2011

  • Engineered by Shafer, Kline and Warren
  • Constructed by C.L. Richardson Company, Inc.
  • Approximately 255 LF of 8” diameter gravity sewer
  • Relocation of the OTSCON WWTP to serve Meadow Village
  • Closure of one lagoon
  • WWTP meets water quality regulations. Compliance is required by July 12, 2011

 

  • Meadow 1

    1/7

    Removing the OTSCON wastewater treatment plant so it can be moved to Meadow Village.

  • Meadow 2

    2/7

    Prep work begins on refurbishing the OTSCON plant.

  • meadow 3

    3/7

    The OTSCON plant ready for transport.

  • Meadow 4

    4/7

    The Meadow Village Lagoon system will be removed once the plant is installed.

  • Meadow 5

    5/7

    Prep work at the Meadow Village Site.

  • Meadow 6

    6/7

    Putting the plant back in the ground at Meadow Village.

  • Meadow 7

    7/7

    A perfect fit.