Spring Park Interceptor

Estimated Project Cost: $444,504
Actual Costs: $403,510
Completed: August 2017

  • Engineered by A Civil Group of Columbia, MO
  • The Construction contract was awarded to Capital RR Excavating
  • Construction of the Spring Park Interceptor Project included
    • The construction of a new sanitary sewer pump station
    • A new 4” force main from the lift station to the City of Columbia sanitary sewer collection system
    • The existing Spring Park lagoon was taken out of service and demolished
  • The users in this area remain BCRSD customers and the BCRSD pays the City of Columbia to treat the wastewater
  • This project was funded by a low interest loan from the State Revolving Fund

 

Spring Park is located off of State Hwy KK south of and adjacent to the Columbia city limits. A project map is posted below.