Rayfield Lagoon Interceptor

Estimated Cost – $980,823
Actual Costs – $618,720

Completion Date: July 2013

  • Engineered by Shafer, Kline and Warren of Columbia, Macon and Kansas City
  • Construction Contract awarded to Capital Railroad Contracting of Columbia, MO
  • Construction of Rayfield Sanitary Sewer Improvements project included
    • The construction of a new sanitary sewer lift station
    • A new four inch diameter force main to the Clearview WWTP
    • And the closure of the Rayfield Subdivision lagoon
  • The project also included replacing the collection system in Rayfield Subdivision to upgrade all lines to 8” diameter, improve accessibility, and minimize the infiltration and inflow (I/I) of storm and ground water.


Rayfield Subdivision is located northwest of Columbia on Creasy Springs Road west of Clearview Subdivision. Location maps and pictures of the project are posted below.

project map

Download Rayfield Interceptor Project
Location Map >

project map

Download Rayfield Interceptor Project Map >

 

Capital Railroad Contracting uses blasting to prepare to dig the lift station site
Capital Railroad Contracting uses blasting to prepare to dig the lift station site
Capital Railroad Contracting uses blasting to prepare to dig the lift station site
Capital Railroad Contracting uses blasting to prepare to dig the lift station site
Capital Railroad Contracting placing one of the wells for the lift station
Capital Railroad Contracting placing one of the wells for the lift station
Capital Railroad Contracting placing one of the wells for the lift station
Capital Railroad Contracting placing one of the wells for the lift station
Capital Railroad Contracting placing one of the wells for the lift station
Capital Railroad Contracting placing one of the wells for the lift station
Shoring is in place in order to allow workers to put the collection pipe together below ground level
The sewer line placement through the woods
Punching the sewer line under the road rather than digging up the pavement
The machine used to bore underground and install the pipe
Capital Railroad Contracting uses blasting to prepare to dig the lift station site