BCSRD Site

Estimated Project Cost:  $588,261

Actual Costs:                 $603,605

Date Completed             March 2017

 

  • Engineered by Engineering Surveys & Services of Columbia, MO
  • The Construction contract was awarded to Hutchins Telecom LLC
  • Construction of the Sunrise Estates Lagoon Interceptor Project included:
    • A new gravity main from both lagoon sites to the City of Columbia sanitary sewer collection system
    • Both existing lagoons were demolished
  • The users in this area remain BCRSD customers and the BCRSD pays the City of Columbia to treat the wastewater
  • This project was funded by a low interest loan from the State Revolving Fund

 

Sunrise Estates is located off of I-70 Drive SE.